Application Notice
Water Equipment
Date: 2021/11/12
Application Items |
Internal Line Diagram Preview |
---|---|
Required Documents |
1.The application form for the internal design drawing of waterequipment is in triplicate.2.A copy of the construction license (copy both front and back).3.Construction start-up report4.One copy of the electronic file (disc) of the internal drawing ofthe water equipment.5. If the preliminary review is th same as preview, theconstruction number will be filled in the original design ofthe preview, and the review result column of the applicationreview form states that the preview diagram of the waterequipment internal chart is the same as the preliminaryreview. And with the addition of the architect's big and smallchapters, the preview work is completed.6. If the design drawings of the water equipment are not sent tothe preliminary review or the original plan is changed, thedocuments for submission include all the documents (1) to(4) and the first preliminary review (2) to (5). |
Flowchart |
|
Application Items |
New Installation |
---|---|
Required Documents |
I. Required Documents:1. Application form, Taiwan Water Corporation Consumer Water SupplyService Contract and Taiwan Water Corporation Personal InformationProtection.(Attached with proof from the water pipe engineering industry)2. Applicant seal & identification card.3. Internal Pipeline Diagram (If the preview is not required, the review is required.)4. Documents for application:(1) Buildings in areas where urban plan is implemented, please prepare anyof the documents below:Builiding use license or entitle deeds.A certificate of finished buildingA certificate of improvement completion in an area where buildingcontrol has not yet been implemented.The letter issued by the local county (city) government or township (cityor district) office which can verify the legitimacy of the old building water use.(2) Buildings in areas where urban plan is not implemented, please prepareany of the documents below:Copy of building, the construction license or registration transcript ofbuilding.Household immigration certificate.Proof of tax filings.Receipt (certificate) of water bill and electricity bill.5.If the external line (water-using facility) requires passing through otherpeople's land, houses, or connecting to other people's water pipes, the applicant shallobtain a letter of consent the approval or recognizance from owner or the management inadvance.6.For commissioned application, the trustee is required to check and verifyrelated information.7.For the construction project started after January 21,2016, if thewater-using facility involved in the review items of “user water-using facility referencenational standard number and name”, its new installation should submit the inspectiondocuments in accordance with National Standards from laboratory which is approved by theTaiwan Accreditation Foundation(TAF).II. Engineering temporary water installation:1. Application form and Taiwan Water Corporation Consumer Water SupplyService Contract.2. Applicant seal & identification card.3. The construction license or engineering contract cover.4. Location map (Cadastral map in principle).5. Various change service application.6. Pay the guarantee fees of temporary water or attach the water fee fullpayment guarantee. (You can make it up before start the use of engineering temporarywater.)7. If the external line (water-using facility) requires passing through otherpeople's land, the applicant shall obtain a letter of consent or recognizance fromlandowner in advance. |
Flow chart |
|
Application Items |
Initiation |
---|---|
Required Documents |
1.Applicant seal2.Building license3.Taiwan Water Corporation Various Change ServiceApplication and Taiwan Water Corporation ConsumerWater Supply Service Contract(For commissionedapplication, the trustee is required to check and verifyrelated information.) |
Application Items |
Remodeling Installation |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4.Taiwan Water Corporation Various Change ServiceApplication |
Application Items |
Termination |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4. Taiwan Water Corporation Various Change ServiceApplication |
Reference |
Applicant must be the owner of the house (Please show theownership of the building as proof). |
Application Items |
Suspension / Restoration |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4. The user who have overdue water fee and be stoppedwater, should pay an one-half of the basic fee, restorationfee and the overdue water fee during the water stopperiod when apply for restoration. If you have stoppedwater for more than two years, you should apply for thenew installation procedure.5.Taiwan Water Corporation Various Change ServiceApplication. |
Reference |
Client who is applying for suspension of the water servicewill not be charged of the basic fees within the suspensionperiod. |
Application Items |
Installment Payment for External Pipeline Construction |
---|---|
Required Documents |
1.Apply for water-using facility external lines expensethrough installment payment shall be subject to thefollowing requirements:(1)You have had household registration in the place ofinstallation.(2)For the newly installation project which the caliber ofwater meter is less than 25mm, and the length ofpipeline less than 20meters.(3)The classification of water supply is common water.2.Apply for installment payment is limited to theconstruction expense, the rest of the expenses should bepaid when applying for the new installation project.3. Installment payment method: Every two months isselected as the payment period, and the maximum periodnot to exceed three years.4.When applying for installment payment, the applicantshould fill out the application form and guarantee, andsubmit the related documents with residency registration.5. The guarantor should meet the following requirements:(1)The guarantor shall be the name of the water owner andshall apply for the owner of the water building; if thename of the water owner is inconsistent with the ownerof the building, the name of the water owner and theowner of the building shall be jointly guaranteed.(2)The guarantor's water address must be in the same TWCdistrict management office as the applicant's applicationaddress.6. The guarantor should check the following documents andgo to the local service (operation) of TWC to handle theinsurance procedures:(1)Identification document(2)The ownership of the building of the guarantor's wateruse location(3)Recently paid water bills |
Application Items |
Installation Proof |
---|---|
Required Documents |
1.Application form2. The previous or current period water bill receipt. |
Reference |
If the user has no outstanding fees, they can apply online orby phone. |
Application Items |
Internal Line Diagram Preview |
---|---|
Required Documents |
1.The application form for the internal design drawing of waterequipment is in triplicate.2.A copy of the construction license (copy both front and back).3.Construction start-up report4.One copy of the electronic file (disc) of the internal drawing ofthe water equipment.5. If the preliminary review is th same as preview, theconstruction number will be filled in the original design ofthe preview, and the review result column of the applicationreview form states that the preview diagram of the waterequipment internal chart is the same as the preliminaryreview. And with the addition of the architect's big and smallchapters, the preview work is completed.6. If the design drawings of the water equipment are not sent tothe preliminary review or the original plan is changed, thedocuments for submission include all the documents (1) to(4) and the first preliminary review (2) to (5). |
Flowchart |
|
Application Items |
New Installation |
---|---|
Required Documents |
I. Required Documents:1. Application form, Taiwan Water Corporation Consumer Water SupplyService Contract and Taiwan Water Corporation Personal InformationProtection.(Attached with proof from the water pipe engineering industry)2. Applicant seal & identification card.3. Internal Pipeline Diagram (If the preview is not required, the review is required.)4. Documents for application:(1) Buildings in areas where urban plan is implemented, please prepare anyof the documents below:Builiding use license or entitle deeds.A certificate of finished buildingA certificate of improvement completion in an area where buildingcontrol has not yet been implemented.The letter issued by the local county (city) government or township (cityor district) office which can verify the legitimacy of the old building water use.(2) Buildings in areas where urban plan is not implemented, please prepareany of the documents below:Copy of building, the construction license or registration transcript ofbuilding.Household immigration certificate.Proof of tax filings.Receipt (certificate) of water bill and electricity bill.5.If the external line (water-using facility) requires passing through otherpeople's land, houses, or connecting to other people's water pipes, the applicant shallobtain a letter of consent the approval or recognizance from owner or the management inadvance.6.For commissioned application, the trustee is required to check and verifyrelated information.7.For the construction project started after January 21,2016, if thewater-using facility involved in the review items of “user water-using facility referencenational standard number and name”, its new installation should submit the inspectiondocuments in accordance with National Standards from laboratory which is approved by theTaiwan Accreditation Foundation(TAF).II. Engineering temporary water installation:1. Application form and Taiwan Water Corporation Consumer Water SupplyService Contract.2. Applicant seal & identification card.3. The construction license or engineering contract cover.4. Location map (Cadastral map in principle).5. Various change service application.6. Pay the guarantee fees of temporary water or attach the water fee fullpayment guarantee. (You can make it up before start the use of engineering temporarywater.)7. If the external line (water-using facility) requires passing through otherpeople's land, the applicant shall obtain a letter of consent or recognizance fromlandowner in advance. |
Flow chart |
|
Application Items |
Initiation |
---|---|
Required Documents |
1.Applicant seal2.Building license3.Taiwan Water Corporation Various Change ServiceApplication and Taiwan Water Corporation ConsumerWater Supply Service Contract(For commissionedapplication, the trustee is required to check and verifyrelated information.) |
Application Items |
Remodeling Installation |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4.Taiwan Water Corporation Various Change ServiceApplication |
Application Items |
Termination |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4. Taiwan Water Corporation Various Change ServiceApplication |
Reference |
Applicant must be the owner of the house (Please show theownership of the building as proof). |
Application Items |
Suspension / Restoration |
---|---|
Required Documents |
1.Identity Document2.Applicant seal3.The previous or current period water bill receipt.4. The user who have overdue water fee and be stoppedwater, should pay an one-half of the basic fee, restorationfee and the overdue water fee during the water stopperiod when apply for restoration. If you have stoppedwater for more than two years, you should apply for thenew installation procedure.5.Taiwan Water Corporation Various Change ServiceApplication. |
Reference |
Client who is applying for suspension of the water servicewill not be charged of the basic fees within the suspensionperiod. |
Application Items |
Installment Payment for External Pipeline Construction |
---|---|
Required Documents |
1.Apply for water-using facility external lines expensethrough installment payment shall be subject to thefollowing requirements:(1)You have had household registration in the place ofinstallation.(2)For the newly installation project which the caliber ofwater meter is less than 25mm, and the length ofpipeline less than 20meters.(3)The classification of water supply is common water.2.Apply for installment payment is limited to theconstruction expense, the rest of the expenses should bepaid when applying for the new installation project.3. Installment payment method: Every two months isselected as the payment period, and the maximum periodnot to exceed three years.4.When applying for installment payment, the applicantshould fill out the application form and guarantee, andsubmit the related documents with residency registration.5. The guarantor should meet the following requirements:(1)The guarantor shall be the name of the water owner andshall apply for the owner of the water building; if thename of the water owner is inconsistent with the ownerof the building, the name of the water owner and theowner of the building shall be jointly guaranteed.(2)The guarantor's water address must be in the same TWCdistrict management office as the applicant's applicationaddress.6. The guarantor should check the following documents andgo to the local service (operation) of TWC to handle theinsurance procedures:(1)Identification document(2)The ownership of the building of the guarantor's wateruse location(3)Recently paid water bills |
Application Items |
Installation Proof |
---|---|
Required Documents |
1.Application form2. The previous or current period water bill receipt. |
Reference |
If the user has no outstanding fees, they can apply online orby phone. |